B25013
(Transportation Asset)
|
The project will resurfaced; Mt Durban Dr, Mt Everest Bl, Mt Gaywas Dr, Mt Foraker Av, Mt La Platta Dr, Mt La Platta Pl, Chateau Dr, Boxwood Dr, Mt Cervin Dr, Diane Ave, Clairemont Mesa Bl, Genesse Av and Lithrop Pl. The scope of work will consist of 2-inch full width grinding and 2-inch AC overlay, with base repair dig-outs as-needed throughout the project.
|
|
Ramos-Banuelos, Jaime
|
|
2
|
|
|
Project Location Map:
|
Click Here
|
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
|
|
Schedule to be determined.
|
If timeline does not show, please click here for instructions on how to resolve this.
|
|
Estimated Project Dollar Amount(1)
|
(1)
|
$906,829
|
Construction Activity
|
(1)
|
$846,829
|
(3)
|
Partially Funded
|
|
TC Construction Co., Inc.
|
(1)
|
Duration to be determined.
|
|
|
See B24002 for Transportation Asset
Click Here
|
See B20005 for Water Asset
Click Here
|
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit:
The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
|
For questions or concerns about the project, call the Public Works Department
construction project information line at (619) 533-4207, email
engineering@sandiego.gov,
or
submit your inquiry online.
Please reference the project name in your inquiry.
|
Form PWD1502
|
11/01/2024
|
|
|