The City of San Diego Project Information Details
Clairemont Mesa East Improv 2 (P)
(Design Bid Build Project)
The City of San Diego
Project Information Details
Clairemont Mesa East Improv 2 (P)
(Design Bid Build Project)
Print Page  
General Information
B25013 (Transportation Asset)
The project will resurfaced; Mt Durban Dr, Mt Everest Bl, Mt Gaywas Dr, Mt Foraker Av, Mt La Platta Dr, Mt La Platta Pl, Chateau Dr, Boxwood Dr, Mt Cervin Dr, Diane Ave, Clairemont Mesa Bl, Genesse Av and Lithrop Pl. The scope of work will consist of 2-inch full width grinding and 2-inch AC overlay, with base repair dig-outs as-needed throughout the project.
Ramos-Banuelos, Jaime
2
CLAIREMONT MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $906,829
Construction Activity
(1) $846,829
(3) Partially Funded
TC Construction Co., Inc.
(1) Duration to be determined.
Additional Remarks
None
See B24002 for Transportation Asset Click Here
See B20005 for Water Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 11/01/2024