Clairemont Mesa East Improv 3 (P)
(Job Order Contract Project)
The City of San Diego
Project Information Details
Clairemont Mesa East Improv 3 (P)
(Job Order Contract Project)
Print Page  
General Information
B25018 (Transportation Asset)
Resurfacing of paving along Mt Alfian Dr and Mt Acadia Blvd.
Sleiman, Alex
2
CLAIREMONT MESA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $112,239
Construction Activity
(1) $56,120
(3) Fully Funded
KTA Construction, Inc.
(1) 13 Months
Additional Remarks
None
See B20043 for Water Asset Click Here
See B20026 for Sewer Asset Click Here
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 12/01/2024