The City of San Diego Project Information Details
Chollas Paint Booth
(Job Order Contract Project)
The City of San Diego
Project Information Details
Chollas Paint Booth
(Job Order Contract Project)
Print Page  
General Information
L14002.5 (Buildings Asset)
The project scope is replace existing Paint Booth build in the 1960s that is inside and integrated in shop facilities. Overall dimensions ~24’ wide / 20’ high / 50’ long. Expect abatement requirements, structural alterations due to exhaust/intake systems, potential upgrades to electrical, gas line connection, water supply for fire protection system, and excavation of concrete to install required reinforcement for the new booth.
Gibson, William
4
MID-CITY:EASTERN AREA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $1,376,000
Construction Activity
(1) $874,271
(3) Fully Funded
Exbon Development Inc.
(1) 14 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 03/01/2024