The City of San Diego Project Information Details
Montezuma Park GDP Amendment
(To Be Determined Project)
The City of San Diego
Project Information Details
Montezuma Park GDP Amendment
(To Be Determined Project)
Print Page  
General Information
P21002 (Parks Asset)
This project Obtains an approved GDP amendment to add a dog park and children’s play area to the park. Due to the relatively small area of the park, the dog park may be best served with the use of synthetic turf. Additional lighting will likely be required. The community may want to add a comfort station to the GDP.
Oliver, Kevin
9
COLLEGE AREA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) Costs to be determined.
Construction Activity
(1) To be determined
(3) Partially Funded
To Be Selected
(1) Duration to be determined.
Additional Remarks
The project is in the preliminary engineering phase and therefore, project’s estimates and schedules are preliminary and subject to change
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.