Chollas Community Park Comfort Station
(Design Bid Build Project)
The City of San Diego
Project Information Details
Chollas Community Park Comfort Station
(Design Bid Build Project)
Print Page  
General Information
S16058 (Buildings Asset)
The project will provide approx.1,800 sq.ft comfort station and concession building. It will also include paving; gravity sewer; potable water lines; plant restoration; electric connection at College Grove Drive extended into the park and a new SDG&E transformer and service with electrical equipment.
Perez, Tony
4
MID-CITY:EASTERN AREA
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $3,134,379
Construction Activity
(1) $2,114,468
(3) Fully Funded
Marcon Engineering Inc
(1) 15 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.