The City of San Diego Project Information Details
University Avenue Complete Street Phase1
(Design Bid Build Project)
The City of San Diego
Project Information Details
University Avenue Complete Street Phase1
(Design Bid Build Project)
Print Page  
General Information
S18001 (Transportation Asset)
This project will provide increased safety on University Avenue between Fairmount Avenue and Euclid Avenue. The project includes installing three roundabouts and medians with enhanced pedestrian crossings. This will also include new pavement, wider sidewalks, and trees along this portion of University Avenue.
Ashrafzadeh, Mastaneh
9
MID-CITY:CITY HEIGHTS
Project Location Map: Click Here
Estimated Project Schedule(1)
Use mouse wheel to zoom in and out of timeline.
Schedule to be determined.
If timeline does not show, please click here for instructions on how to resolve this.
 
Estimated Project Dollar Amount(1)   
(1) $12,380,291
Construction Activity
(1) $7,881,066
(3) Fully Funded
West Coast General Corporation
(1) 31 Months
Additional Remarks
None
Notes:
1. The cost and schedule data shown here are the City’s current best estimates and subject to frequent change. Changes (if any) are updated once a month.
2. To learn more about Capital Improvement Projects, visit: The Citizens Guide to the Capital Improvement Program.
3. Fully Funded means there are sufficient funds for construction phase and Partially Funded means that there are insufficient funds for construction phase.
For questions or concerns about the project, call the Public Works Department construction project information line at (619) 533-4207, email engineering@sandiego.gov, or submit your inquiry online.
Please reference the project name in your inquiry.
Form PWD1502 10/01/2024